Supreme Court Spotlight – Nominal liquidated damages clauses
In Capello v Hammond & Simonds NSW Pty Ltd [2020] NSWSC 1021 His Honour Justice Ball considered the entitlement of a homeowner to general delay damages in circumstances where the contract stipulated liquidated damages of $1 a day. In this case, Ball J held that the clause in dispute, within an industry-standard contract, was void. … Continue reading Supreme Court Spotlight – Nominal liquidated damages clauses